Question: 1 / 160

What is required before any permit can be issued for land-disturbing activities?

Submission of a bond

Approval from the Secretary of State

Completion of a public hearing

Inclusion of an approved ESC plan and certification

Prior to the issuance of any permit for land-disturbing activities, it is essential to have an approved Erosion and Sediment Control (ESC) plan and certification. This requirement is rooted in the need to manage and minimize soil erosion and sedimentation that can result from land disturbances. An approved ESC plan outlines the measures that will be employed to control erosion and to protect water quality, ensuring that the site is managed in an environmentally responsible manner.

The inclusion of an approved ESC plan is a critical aspect of the permitting process as it helps to ensure compliance with state regulations and demonstrates that the project will adhere to established standards for managing erosion and sedimentation. This plan not only provides guidelines for the activities but also helps to mitigate potential impacts on the surrounding environment.

In contrast, while other requirements like bond submissions, public hearings, or specific approvals may be relevant in some contexts, they do not fulfill the fundamental need for a robust erosion and sediment control strategy prior to permitting land-disturbing activities.